Mega Warehouse project sticks to plan in rainy season, completing nearly 9,500 m2 of steel structure

  • 30-05-2017
  • Project News

Regardless of bad weather, nearly 9,500 m2 of steel structure of the main factory of Mega Warehouse cold storage was completely installed last week, ensuring the project schedule as set before.

According to report by Project Department, the construction of Mega Warehouse cold storage had encountered many difficulties due to continuous and heavy rains. Thus, Board of Management of Toda Industries and Meito Vietnam had implemented numerous synchronous measures to ensure safety in the construction site such as installing pumps for drainage, providing supervisors and workers with raincoats and personal protective equipment. Walking routes were also modified so that workers can easily and safely perform their jobs.

In June, Toda Industries will conduct the corrugated iron roofing, flooring and installation of wall panels as well as execute other items inside Mega Warehouse storage.

Pictures of the project are shown below.

Mega Warehouse project sticks to plan in rainy season

Mega Warehouse project sticks to plan in rainy season

Mega Warehouse project sticks to plan in rainy season

Nearly 9,500 m2 of steel structure of the main storage of Mega Warehouse was completely installed, ensuring the project schedule as set before.